Installation Guide
- Categories:Related applications
- Time of issue:2021-04-01 15:32:37
- Views:0
Ceiling series
Wall bonding series
1. The cement mortar toweling course shall be solid, flat and free of hollowing; and the quality reaches Code for Construction Quality Acceptance of Building Decoration.
2. Prepare the binder dry powder and water proportionally, mix in mortar mixer for 3-5min, still for 5-10min, and use after mixing uniformly.
3. The insulating decoration board shall be horizontally paved along the horizontal direction according to the reserved typesetting position from top to down, the slab joint width shall be designed by typesetting, and the joint width shall be generally 6mm.
4. The binder shall be smeared on the back of insulating decoration board with point frame method, to guarantee that the bond area shall be more than 40%.
5. The deviation of flatness of sticking board shall be less than 3mm, and the height difference of adjacent boards shall not be more than 1mm. The slab joint shall be horizontal, flat and vertical, and the deviation shall be less than 1mm.
Light steel keel partition series
Wall dry hanging series
Scan the QR code to read on your phone
CONTACT INFORMATION
TEL
ADD
Copyrights © 2021 Sinoma (Yichang) Energy Conservation New Material Co., Ltd 鄂ICP备********号